Drilling and testing of geothermal wells in Geiselbullach, Germany completed
Source ↗
👁 0
💬 0
The drilling phase of the geothermal heating project in Olching-Geiselbullach in Germany has been completed, with well testing results indicating positive findings. Work has now started on installing the pumps and constructing the district heating station, and commercial heat supply is expected to start no later than the 2027 heating season.
On August 2026, the performance tests of the second well were completed, about six months after drilling work officially started. The well discharged therma
On August 2026, the performance tests of the second well were completed, about six months after drilling work officially started. The well discharged therma