The Trump administration told the Supreme Court about two weeks ago that construction of a new White House East Wing was “65% finished.” Officials used that figure as part of their argument that the work had already gone too far for the court to halt it. The Washington Post reported that a confidential agreement with contractor Clark Construction, which the newspaper reviewed, set a different measure. The agreement, finalized before Clark started demolition last October, says payments to the